38 Combined Assurance Report 2019/20 PDF 324 KB
Additional documents:
Minutes:
Members considered the Authority’s Combined Assurance report for 2019/20.
The following points were highlighted by the Corporate Policy Manager:
· This report would normally be tabled during the March meeting, but was ready earlier for this year;
· The Combined Assurance report was an annual exercise undertaken by partners from Internal Audit. It was a record of assurance measured against critical activities, IT, key projects and partnerships and others. After speaking to the relevant managers, a level of assurance was given to different work strands.
There were 119 different areas across the report; 72% of activities in the report were performing well (green assurance), 25% of areas in the report were in need of attention (amber), and 3% were not performing well (red);
· There were four items listed as ‘red’; none of these related to front-facing transactional services. These four items were:
o Strategic capacity – changes at Executive Director level;
o Agri food sector – the project cannot currently proceed due to landowner restrictions;
o Educational attainment – inability to raise local levels;
o ICT Security and Information Governance – the arrangements were ineffective;
· All of the ‘amber’ risks detailed in the report were known to management. It would need to be ensured that sufficient actions were taken to address these risks;
· The conclusion from partners at Internal Audit and WLDC management was that the findings were positive, and the governance framework was acting well.
RESOLVED to:
1) Be assured that the findings illustrate that the Council’s governance framework was operating effectively;
2) Approve the report.